Category:

Highest head utilization in Sri Lanka for a small hydro power project

Being the highest head utilization in Sri Lanka for a small hydro power project, Loggal oya phase 2 project utilizes a gross head of 500m and a flow of 1.2 Cumecs to generate 5,000kW of electrical power.

The project comprise of 2500m long steel penstock. The  design  pressure closer to the turbine is 75 bar, resulting very heavy steel thickness for pipes. The project comprise of high quality European turbines & generators (Twin Jet Pelton).

The project is located in isolated village with minimum infrastructure. (Akiriya Village, Badulla District, UVA Province). The project construction team responsible for penstock faced many challenges when constructing the steel penstock line without any motorable access.

TECHNICAL & FINANCIAL DATA

Gross Head : 500m Net Head : 480m Design Flow : 1.2m3/s
Turbine Type : Pelton Turbine 1  : 3600kW Turbine 2 : 1450kW
Total Elec. Output : 5,000kW Channel length : 300m Penstock length : 2500m
Catchment : 12 Sq.km Catchment rainfall : 2500mm Annual Energy : 13GWh
Investment : USD 7.2Mn Com. Operation started : JUN 2008 E&M Make ; European